Item Coversheet
Item Number:DISCUSSION ITEMS- II.-1.
Committee Meeting Date:11/6/2017
  
City of Roeland Park
Action Item Summary

Date:10/27/2017 
Submitted By: Jose Leon 
Committee/Department: Roe 2020 Planning Committee
Title:Roe 2020 Visioning Process Results and Conceptual Design Presentation (est. 45 min.)
Item Type:Presentation



Recommendation:

Staff recommends approval of design concepts to be incorporated into final plans that are with in the $8.2 million budget established for this project. 

Details:

The Governing Body approved staff to work with George Butler Associates (GBA) and Vireo through Visioning Phase to identify our communities priorities for our Roe Blvd. project.  In doing so, we developed an Advisory Committee made up of business leaders, governing body members, transit community members, KDOT staff, WYCO staff, and residents.  We held 3 Advisory Committee meetings and 2 Public Meetings.  Vireo established an online presence for the project to accept feedback and comments from the Public using Facebook and roeblvd.digicate.com

 

 

In total, we had 32 people attend our public meetings and offer comments/concerns.  Currently, 355 respondents have participated in opinion surveys and our social media has reached thousands of people.  Throughout the Visioning Phase there were two main items that continually became main points of discussion:  1) Maintain the traffic capacity of Roe Blvd. for vehicular traffic to safely use in our City. 2) Make Roe Blvd. a more walkable and safer corridor for our non-vehicular users to connect both half's of our City.  GBA and Vireo produced concept alternatives for intersections and roadway typical sections to show how we can achieve our community’s goals and we discussed alternatives in our advisory committee meetings and our public meetings. 

 

We have completed our Visioning Phase and are providing the governing body the following recommendations to begin preliminary design:

  • Keep four lanes of traffic to maintain capacity through our City
  • Remove unnecessary turn lanes with low volumes of turn movements to make the vehicular traffic more efficient
  • Remove unnecessary traffic signals
  • Construct a Multiuse (minimum 8' wide) trail along Roe Blvd.  
  • Maintain and improve median uses for pedestrian crossing safety areas
  • Beautification and Gateway Elements improvements, along with improvements along corridor

 

The recommendations are a combination of feedback and studies performed on the Corridor over the last year.  GBA will begin their preliminary design efforts once the Governing Body approves the recommendations.  The Design schedule for this project is tentatively:

 

  • Preliminary Design – November 2017 – October 2018
  • 60% Plans Complete (KDOT Field Check) - November 2018
  • Final Design – December 2018 – August 2019
  • Final Plans Complete – August 2019
  • Advertise  - October 2019
  • Letting – November 2019
  • Construction - 2020

 

The total project cost for 2020 Roe Blvd project is $8.2 Million dollars.  As we get into preliminary design, staff will work with the design team to ensure our project is within budget and on schedule.


How does item relate to Strategic Plan?

Project implements the City strategic goals to improve and maintenance City infrastructure.

How does item benefit Community for all Ages?

Project will consider a wide variety of Community for all Ages features and enhancements.
Additional Information

Funding for the project is as follows.

 

STP = $4,662,500 (Federal)

CARS = $1,212,250 (County)

TIF 2 = $545,000 (City)

TIF 1 = $1,107,577 (City)

Sp. Streets = $665,986 (City)

 

Total Project = $8,193,313.00

ATTACHMENTS:
DescriptionType
Roe 2020 Visioning Process PresentationPresentation