Item Coversheet
Item Number:New Business- VI.-B.
Committee Meeting Date:5/4/2020
  
City of Roeland Park
Action Item Summary

Date:4/24/2020 
Submitted By:  
Committee/Department: 
Title:Approve Extending Vertical Construction and Final Completion Deadlines for Sunflower Medical
Item Type:



Recommendation:

Staff recommends approving the extension per the attached agreement amendment. 

Details:

Sunflower has requested the City consider extending their “vertical construction start date” from May 1 to May 25. It is a reasonable request considering the unusual circumstances we are living in. This adjustment would also change the completion date by the same number of days (they have 1 year from the start of vertical construction to complete construction.  Steve Mauer has reviewed the agreement and has prepared an amendment to the sale agreement that would afford this change.  Per Sunflower their request is driven by a longer than expected review and approval process for the sanitary sewer realignment and underground electric relocation improvements.



Financial Impact

Amount of Request:  N/A
Budgeted Item?  Budgeted Amount:  
Line Item Code/Description:  

Additional Information


How does item relate to Strategic Plan?



How does item benefit Community for all Ages?

ATTACHMENTS:
DescriptionType
2nd Amendment to Land Sale AgreementCover Memo